1) The entire construction plan for the anti-seepage wall of the reservoir has a good anti-seepage effect,
requires less investment, and is easy to construct. It is necessary and feasible to implement it in plain reservoirs.
2) During the process of laying large-area geomembranes, the main failure forms of geomembranes include
tear failure, burst and burst failure, tensile failure, corresponding hole defects, mechanical and manual operation
errors, and natural conditions, etc. In response to its failure forms and causes, material quality management should
be carried out from several aspects, including material selection, production tests, quality inspection and evaluation,
and quality control at key links.
3) When using geomembrane for anti-seepage in highland conditions, reliable drainage measures must be taken.
Based on the actual engineering geological and underground hydrogeological conditions, calculation and analysis
carried out on the basis of experiments. From both economic and technical perspectives, the drainage scheme design
of the site section meets the requirements of the engineering construction.
4) During the large-scale membrane laying construction of the entire warehouse, conduct production tests for the
laying of geotextile membranes to determine construction indicators, reasonable mechanical equipment and personnel
combinations, etc. ; Clarify the construction technical plans for the main links such as the surface treatment of the base
layer and the excavation of blind ditches, the laying and sewing of geotextiles, the laying and welding of geomembranes,
and the installation of drainage and exhaust check valves. Formulate the main measures for construction management
from aspects such as quality management, progress management, safety production, and construction during the rainy
season.
Since the water storage and operation began, the anti-seepage effect of the project has met the design requirements,
and the actual operation of the project has been good. Its engineering construction technology and management methods
have certain theoretical guiding significance and can provide certain references for similar projects in the future.